What would happen if activities B and D each took 5 extra days to complete instead of the expected duration?

Looking for some help? We have it all. Great price and impressive quality

For This or a Similar Paper Click To Order

Learning Goal: I’m working on a management report and need an explanation and answer to help me learn.
Given the following information, answer the questions about this project:
Activity
Expected Duration
Predecessors
A
4 days

B
9 days
A
C
11 days
A
D
5 days
B
E
3 days
B
F
7 days
C
G
3 days
D, F
H
2 days
E, G
I
1 day
H
Draw the network as a Gantt chart.
What is the critical path? Which activities have slack time?
What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?

Looking for some help? We have it all. Great price and impressive quality

For This or a Similar Paper Click To Order

Leave a comment

Your email address will not be published. Required fields are marked *